Construction Projects

Capital Projects



South Denver

  • Construction is underway
  • DOLA Grant awarded.
  • Paving is currently underway.
  • Project completion is mid October 2017.
  • Project extends from Kahil Street south to the city limits.
  • Detours and closures possible through October, your patience is appreciated.
  • Project is complete.

2018 Sidewalk Repair Project


  • List of areas to be repaired is being compiled.
  • Expected release to contractor at the end of May 2018.

Factory Circle

Paving Project

  • Paving project will go out to bid early 2018.
  • Contractor has been awarded.
  • Construction is due to start the second week in May 2018,
  • Anticipated completion the beginning of June 2018.

9th Street Waterline Replacement


  • Currently under contract.
  • DOLA grant has been received.
  • Estimated project start late September 2017.
  • Road closures between Northrup Avenue and College Avenue (County Road 29.5)
  • Gravity main complete and in service.
  • High pressure line is currently being repaired. Anticipated completion early 2018.
  • Project is complete.

County Road 23.5

  • Under in-house design phase.
  • Projected for Fall 2018
  • Project includes a regrade and drainage improvements.

County Road 12 Improvements


  • The City of Fort Lupton will be working with Anadarko to repave from South Denver Avenue east to County Road 29. Improvements will include a water line extension, drainage improvements, and widening of the road similar to the South Denver widening project of 2017.
  • Currently pursuing DOLA grant with Anadarko matching funds.
  • In interim, Anadarko is responsible for grading and maintaining this area of road. This is in accordance with previously established agreement with Anadarko.

Well 26 Waterline Project

  • Water line is non-potable water
  • Extends from well system manifold. Please see the map.
  • Currently out for bid.
  • Construction anticipated to start June 2018.
  • Anticipated completion - August 2018.

Non-City Utility Work To find possible construction impacts please contact the utility company conducting the work:

Century Link 1-800-526-3557
Xcel Energy at 1-800-895-4999 
United Power