Construction Projects

Capital Projects

Mustang Avenue Repair

Water Meter Upgrades

  • Pilot program set to start with 10 sites to test software integration and usage readibility.
  • 500 water meters will receive upgraded components in 2020.

Greenwood Court Repaving

  • Anticipated start May 2020
  • Project is complete. 

7th Street from Hoover Avenue to McKinley Avenue Repaving

  • Project is currently underway
  • Project is complete. 

Broadway Avenue Sanitary Sewer Line from 8th Street to 9th Street and Repave

  • Mostly completed, a few patch-backs are still needed. 
  • Project is complete. 

Bike Trail

  • Currently in planning stage

College Avenue at 9th Street Paving

  • Currently under design.
  • Project is being coordinated with developer.
  • Anticipated construction Spring 2021.

Coyote Creek Filing 2 & 3 Irrigation Booster Pumps

  • Project has been awarded
  • Filing 2 booster pump set to be operational in late May 2020.
  • Filing 3 booster pump set to be operational in mid June 2020.
  • Contractor will be installing pumps July 2020.
  • Pumps are installed. 
  • Pending United Power changes to connection.

Kahil Place Drainage Improvements

  • Project anticipated to go out to bid July 2020.
  • The paving phase of this project is anticipated to start September 2020.
  • Bid awarded to JBS Pipeline.

County Road 23.5

  • Under in-house design phase.
  • Project includes a regrade and drainage improvements.

6th Street from Denver Avenue to Rail Road Right of Way

  • Delayed due to utility changes on Denver Avenue
  • Project is currently on hold.


Non City Developments

College Avenue Waterline Extension

  • The waterline at Highway 52 crossing under into the Mountain Sky Subdivision
  • Work anticipated to begin the week of June 29, 2020.
  • Anticipated completion October 2020.

South Rollie Paving

  • Paving from County Road 10 to County Road 8 anticipated to start late May 2020.
  • Project is complete.

Mountain Sky Subdivision (South College Avenue)

  • 1st Phase near completion.
  • Pending sale to DR Horton for home construction.
  • Phase II will begin September 2020.

Cottonwood Greens Subdivision (north of 9th Street & east of Fulton Ditch)

  • Project anticipated to start Fall 2020

Fulton Village

  • Baessler Homes
  • Infrastructure nearly complete
  • Fulton Avenue paving restoration anticipated to start early August 2020

United Power 9th Street Project

  • Estimated start 09/14/2020
  • Estimated completion 11/13/2020
  • Retiring overhead electrical line. New underground line will be installed in private easement. Work will be from Birch Ct. to College Avenue.
  • Expect one lane roads in the work area.


Non-City Utility Work

To find possible construction impacts please contact the utility company conducting the work:

Century Link 1-800-526-3557

CDOT Projects

Xcel Energy at 1-800-895-4999

United Power